Question 11 Mark
Controlling always involves taking corrective action in response to deviation. (True/ False)
Answer
False.
Explanation:
As no corrective action is required in controlling if the deviations are within the acceptable limits.
View full question & answer
Question 21 Mark
Controlling is a continuous activity. (True/ False)
Answer
True.Explanation:
As the actual performance is compared with the standard performance on a continuous basis and it brings to light the deviations, if any.
View full question & answer
Question 41 Mark
Controlling is unaffected by the changes in external factors of business environment. (True/ False)
Answer
False.
Explanation:
As control is affected by changes in external factors as no enterprise can control it. This is a limitation of controlling.
View full question & answer