Differentiate between standing and single use plans.
|
S. No.
|
Basis
|
Standing plans
|
Single use plans
|
|
1.
|
Period
|
They are formed for a long period.
|
They are formed for a short period and discarded when the assignment/ project is Over.
|
|
2.
|
Scope
|
They have a wide scope as they involve the whole organisation in its scope.
|
They have a narrow scope and they are formulated for a specific project/ assignment/ situation.
|
|
3.
|
Frequency of use
|
These are repetitive in nature.
|
They are one time plan, not used for recurring situations.
|
|
4.
|
Examples
|
Policies, procedures, methods, etc.
|
Objectives, budgets, etc.
|