Questions

Solve the Following Question.(3 Marks)

Take a timed test

6 questions · self-marked practice — reveal the answer and mark yourself.

Question 13 Marks
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine, and a tapping, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also, find the total elapsed time and the idle time for every machine.
JobSHAPING (MINUTES)DRILLING (MINUTES)TRAPPING (MINUTES)
113318
21884
38613
42368
View full question & answer
Question 23 Marks
A toy manufacturing company has five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
Type12345
Machine A1620121422
Machine B1012468
Machine C818161210
Solve the problem for minimizing the total elapsed time.
View full question & answer
Question 33 Marks
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the times each man would take to perform each task is given in the effectiveness matrix below.
IIIIIIIV
A7252610
B1227325
C37181714
D1825239
How should the tasks be allocated, one to a man, as to minimize the total man-hours?
View full question & answer
Question 43 Marks
An insurance company receives three types of policy application bundles daily from its head office for data entry and filing. The time (in minutes) required for each type for these two operations is given in the following table:
Policy123
Data Entry90120180
Filing140110100
Find the sequence that minimizes the total time required to complete the entire task. Also, find the total elapsed time and idle times for each operation.
View full question & answer
Question 53 Marks
A company has three jobs on hand, Each of these must be processed through two departments, in the AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job each department
JobIIIIII
Department A865
Department B834
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
View full question & answer
Question 63 Marks
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R, and S. The processing cost of each job for each machine is given in the following table:
JobsMACHINES (PROCESSING COST IN ₹)
IIIIIIIV
P31253329
Q25242321
R19212324
S38363440
Find the optimal assignment to minimize the total processing cost.
View full question & answer