Q 1MCQ1 Mark
The assignment problem is said to be unbalanced if
  • A
    Number of rows is greater than the number of columns
  • B
    Number of rows is lesser than number of columns
  • C
    Number of rows is equal to the number of columns
  • Both (a) and (b)

Answer: D.

View full solution
Q 2MCQ1 Mark
Using the Hungarian method the optimal assignment obtained for the following assignment problem to minimize the total cost is:
AGENTJOB
ABCD
110121525
214111932
318212329
415202628
  • $1- C , 2- B , 3- D , 4- A$
  • B
    $1- B , 2- C , 3- A , 4- D$
  • C
    $1- A , 2- B , 3- C _1 4- D$
  • D
    $1- D , 2- A , 3- B , 4- C$

Answer: A.

View full solution
Q 3MCQ1 Mark
To use the Hungarian method, a profit maximization assignments problem requires
  • Converting all profit to opportunity losses
  • B
    A dummy person or job
  • C
    Matrix expansion
  • D
    Finding the maximum number of lines to cover all the zeros in the reduced matrix

Answer: A.

View full solution
Q 4MCQ1 Mark
In solving 2 machine and n jobs sequencing problem, the following assumption is wrong
  • A
    No passing is allowed
  • B
    Processing times are known
  • C
    Handling times is negligible
  • The time of passing depends on the order of machining

Answer: D.

View full solution
Q 5MCQ1 Mark
The Assignment Problem is solved by
  • A
    Simple method
  • Hungarian method
  • C
    Vector method
  • D
    Graphical method

Answer: B.

View full solution
The maximization assignment problem is transformed to minimization problem by subtracting each entry in the table from the ___________ value in the table.
View full solution
The time interval between starting the first job and completing the last, job including the idle time (if any) in a particular order by the given set of machines is called ___________
View full solution
A foreman wants to process 4 different jobs on three machines: a shaping machine, a drilling machine, and a tapping, the sequence of operations being shaping-drilling-tapping. Decide the optimal sequence for the four jobs to minimize the total elapsed time. Also, find the total elapsed time and the idle time for every machine.
JobSHAPING (MINUTES)DRILLING (MINUTES)TRAPPING (MINUTES)
113318
21884
38613
42368
View full solution
A toy manufacturing company has five types of toys. Each toy has to go through three machines A, B, C in the order ABC. The time required in hours for each process is given in the following table.
Type12345
Machine A1620121422
Machine B1012468
Machine C818161210
Solve the problem for minimizing the total elapsed time.
View full solution
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the times each man would take to perform each task is given in the effectiveness matrix below.
IIIIIIIV
A7252610
B1227325
C37181714
D1825239
How should the tasks be allocated, one to a man, as to minimize the total man-hours?
View full solution
An insurance company receives three types of policy application bundles daily from its head office for data entry and filing. The time (in minutes) required for each type for these two operations is given in the following table:
Policy123
Data Entry90120180
Filing140110100
Find the sequence that minimizes the total time required to complete the entire task. Also, find the total elapsed time and idle times for each operation.
View full solution
A company has three jobs on hand, Each of these must be processed through two departments, in the AB where
Department A: Press shop and
Department B: Finishing
The table below gives the number of days required by each job each department
JobIIIIII
Department A865
Department B834
Find the sequence in which the three jobs should be processed so as to take minimum time to finish all the three jobs. Also find idle time for both the departments.
View full solution
Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
Jobs (Processing times in minutes)
IIIIIIIVVVIVII
Machine A126511576
Machine B7894783
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle time for both machines.
View full solution
A chartered accountant’s firm has accepted five new cases. The estimated number of days required by each of their five employees for each case are given below, where-means that the particular employee can not be assigned the particular case. Determine the optimal assignment of cases of the employees so that the total number of days required to complete these five cases will be minimum. Also, find the minimum number of days.
EmployeeCases
IIIIIIIVV
E164578
E27-869
E3867910
E457-46
E595310-
View full solution
Consider the problem of assigning five operators to five machines. The assignment costs are given in the following table.
OperatorMachine
12345
A66-37
B85345
C1046-4
D83783
E768102
Operator A cannot be assigned to machine 3 and operator C cannot be assigned to machine 4. Find the optimal assignment schedule.
View full solution
The estimated sales (tons) per month in four different cities by five different managers are given below:
ManagerCities
PQRS
I34363335
II33353133
III37393535
IV36363434
V35363533
Find out the assignment of managers to cities in order to maximize sales.
View full solution
A dairy plant has five milk tankers, I, II, III, IV & V. These milk tankers are to be used on five delivery routes A, B, C, D & E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
IIIIIIIVV
A150120175180200
B125110120150165
C130100145160175
D40407070100
E4525607095
How should the milk tankers be assigned to the chilling centre so as to minimize the distance travelled?
View full solution