Find the sequence that minimizes the total elapsed time to complete the following jobs. Each job is processed in order AB.
Jobs (Processing times in minutes)
IIIIIIIVVVIVII
Machine A126511576
Machine B7894783
Determine the sequence for the jobs so as to minimize the processing time. Find the total elapsed time and the idle time for both machines.
View full question & answer
Question 24 Marks
A chartered accountant’s firm has accepted five new cases. The estimated number of days required by each of their five employees for each case are given below, where-means that the particular employee can not be assigned the particular case. Determine the optimal assignment of cases of the employees so that the total number of days required to complete these five cases will be minimum. Also, find the minimum number of days.
EmployeeCases
IIIIIIIVV
E164578
E27-869
E3867910
E457-46
E595310-
View full question & answer
Question 34 Marks
Consider the problem of assigning five operators to five machines. The assignment costs are given in the following table.
OperatorMachine
12345
A66-37
B85345
C1046-4
D83783
E768102
Operator A cannot be assigned to machine 3 and operator C cannot be assigned to machine 4. Find the optimal assignment schedule.
View full question & answer
Question 44 Marks
The estimated sales (tons) per month in four different cities by five different managers are given below:
ManagerCities
PQRS
I34363335
II33353133
III37393535
IV36363434
V35363533
Find out the assignment of managers to cities in order to maximize sales.
View full question & answer
Question 54 Marks
A dairy plant has five milk tankers, I, II, III, IV & V. These milk tankers are to be used on five delivery routes A, B, C, D & E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
IIIIIIIVV
A150120175180200
B125110120150165
C130100145160175
D40407070100
E4525607095
How should the milk tankers be assigned to the chilling centre so as to minimize the distance travelled?
View full question & answer
Question 64 Marks
A publisher produces 5 books on Mathematics. The books have to go through composing, printing, and binding was done by 3 machines P, Q, E. The time schedule for the entire task in the proper unit is as follows.
BookABCDE
Machine P49865
Machine Q56234
Machine R8106711
Determine the optimum time required to finish the entire task.
View full question & answer
Question 74 Marks
A company has a team of four salesmen and there is four districts where the company wants to start its business. After taking into account the capabilities of salesmen and the nature of districts, the company estimates that the profit per day in rupees for each salesman in each district is as below:
SalesmanDistrict
1234
A16101211
B12131515
C15151114
D13141415
Find the assignments of a salesman to various districts which will yield maximum profit.
View full question & answer
Question 84 Marks
Four new machines $M_1, M_2, M_3$, and $M_4$​​​​​​​ are to be installed in a machine shop. There are five vacant places $A, B, C, D,$ and $E$ available. Because of limited space, machine $M_2$​​​​​​​ cannot be placed at $C$ and $M_1$​​​​​​​ cannot be placed at $A$. The cost matrix is given below.
Machines Places
  A B C D E
M1 $4$ $6$ $10$ $5$ $6$
M2 $7$ $4$ - $5$ $4$
M3 - $6$ $9$ $6$ $2$
M4 $9$ $3$ $7$ $2$ $3$
Find the optimal assignment schedule.